baab

KIIFB PRPJECTS

Improvements to Parapram Olayambalam sixth mile road km 0/000 to 5/167 and km 5/900 to 9/405 in Kannur District

Overview

for providing DBM and BC, The strengthening of the road with GSB and WMM after scarification and application of prime coat, tack coat. Interlock on shoulders at parking bays, construction of culvert, side protection works.
Road markings, sign boards, Crash barriers have been provided.

Project

mprovements to Parapram Olayambalam sixth mile road km 0/000 to 5/167 and km 5/900 to 9/405 in Kannur District

Department

PMU - KRFB (Agreement authority)
KIIFB (Funding agency)

Value

12.04 (Amount in crore)

Date of Commencement Work

14-12-2017

Date of Completion

13-06-2019