for providing DBM and BC, The strengthening of the road with GSB and WMM after scarification and application of prime coat, tack coat. Interlock on shoulders at parking bays. The shoulders strengthened with concrete and
earth filling. Provision for concrete drainage system with duct, construction of culvert, side protection works. Side protection will be done with DR walls at some chainages. Road markings, sign boards, etc. is also included. Crash
barriers have been provided.

Project

KIIFB 2016-17 Improvement to Thottilpalam Kunduthode road from km 0/000 to 6/200

Department

PMU - KRFB (Agreement authority)
KIIFB (Funding agency)

Value

14.47 (Amount in crore)

Date of Commencement Work

24-02-2022

Date of Completion

31-12-2023